APPROVED
Director of the municipal enterprise Ivano-Frankivsk Regional Council operating assets
Kostyshyn VI.
"___" __________ ___ 20 g.
work plan
utility company, Ivano-Frankivsk Regional Council operating assets
on 2016 year
Number s / n | The content of the event | The estimated cost of
(thousand. UAH. ) |
Responsibility | Term
implementation |
1 | 2 | 3 | 4 | 5 |
1 | In order to meet the regional target program of support of the utility company, Ivano-Frankivsk Regional Council operating assets administrator submit proposals main regional budget on budget allocations for 2016 year | According to budget allocations | V.Kostishin
V.Pasichnyk |
|
in the administrative building on the street. Hrushevskoho, 21 in Ivano-Frankivsk | ||||
2. | Estimating the repair of the boiler house roof coating | 357,0 th. UAH. | A.Kudybin | 1-quarter |
3 | Examination of project documentation for the repair of the boiler house roof coating | |||
4 | Ремонт дахового покриття над котельнею (600 м.кв.) | |||
5 | Складання кошторису на заміну вікон в коридорах на 4-8 floors, the Department of Health Ivano-Frankovsk, lobby hall on 2 floor |
99,50 th. UAH. |
N.Korolchuk | February |
6 | Заміна вікон (в коридорах на 4-8 floors, the Department of Health Ivano-Frankovsk, lobby hall on 2 поверсі) | 2-quarter | ||
7 | Painting walls in the corridors 6,7,8 floors, sanding and varnishing the parquet at elevators | 15,0 th. UAH. | N.Korolchuk | January February |
8 | Repairs, sanding and varnishing of parquet in boardrooms | 15,0 th. UAH. | N.Korolchuk | 2-quarter |
9 | Elaborate Scheme CCTV |
120,0 th. UAH. |
V.Gava
V.Pasichnyk |
1-quarter |
10 | Розробити кошторис на виконання робіт по встановленню відеоспостереження | 2-quarter | ||
11 | Придбання та встановлення системи відеоспостереження на 1-й пост та поновлення її роботи | 3-quarter | ||
12 | Забезпечення розхідними матеріалами для належної роботи комп’ютерної техніки | 20,0 th. UAH. | V.Budzik | during the year |
1 | 2 | 3 | 4 | 5 |
13 | Preparation and submission of documents for the manufacture of technical documentation on the installation of fire alarm | 150,0 th. UAH. | A.Kudybin | 4-quarter |
14 | Installation of fire alarm systems | 2, 0 million. UAH | A.Kudybin | 4-quarter |
15 | Replacing the carpet in the stairwell 1-8 floors | 45,0 th. UAH. | S.Gayduk | 3-quarter |
16 | Obtaining permission to use tap "Pioneer" | 6,0 th. UAH. | A.Kudybin | February-March |
17 | To conclude an agreement with a licensed organization for repair of elevators | 50,0 th. UAH. | V.Gava | 1-quarter |
18 | To conclude an agreement on the maintenance and calibration of gauges Metrology | 20,0 th. UAH. | A.Tymchiy | August |
19 | To conclude an agreement on maintenance of the boiler house roof | 9,0 th. UAH. | A.Kudybin | 1-and, 4-quarter |
20 | To conclude an agreement on the calibration of ground contour elevators |
25,0 th. UAH. |
V.Gava | 2-quarter |
21 | Ensure calibration contour grounding boiler | |||
22 | Provide and carry out calibration and replacement of the new facilities for electricity meters and current transformers | 25,0 th. UAH. | V.Gava | 1-quarter |
23 | Укласти угоду на проведення експертизи посудин під тиском (дахова котельня, pump receivers) | 10,0 th. UAH. | A.Tymchiy | 1-4-quarter |
24 | In order to save electricity, to replace fluorescent lamps to LED in the corridors | 80,0 th. UAH. | V.Gava | 2-3-quarter |
25 | In order to save electricity, to replace incandescent lamps in the hall 500 places on saving | 20,0 th. UAH. | V.Gava | 2-quarter |
26 | Ensure agreement on the examination of elevators number 7,8, and repair work | 25,0 th. UAH. | V.Gava | 2-3-quarter |
27 | Carry out repairs and replacement lamps Outdoor lighting administrative building, restoration trident | 20,0 th. UAH. | V.Gava
N.Korolchuk |
2-quarter |
28 | To conclude an agreement to replace and repair valves Fire system | 8,0 th. UAH | A.Tymchiy | August |
29 | To replace pumps for water supply for fire systems | 70,0 th. UAH | A.Kudybin | 2-quarter |
30 | Укласти угоди на проведення навчання на курсах підвищення кваліфікації працівників відповідних робітничих професій (при необхідності) | 10,0 th. UAH. | A.Tymchiy | during the year |
31 | Провести передоплату за друковану кореспонденцію (на наступний рік)
|
10,0 th. UAH. | V.Pasichnyk | December |
1 | 2 | 3 | 4 | 5 |
in the administrative building on the street. Independence, 46 in Ivano-Frankivsk | ||||
32 | Виготовлення проектно-кошторисної документації на встановлення модульної котельні (на твердому паливі) | 90,0 th. UAH. | A.Kudybin | 1-quarter |
33 | Встановлення модульної котельні (на твердому паливі) | 1,5 mln. | S.Babelskyy
A.Kudybin |
2-3-quarter |
34 | Estimating the manufacture and purchase fencing materials, installing fences |
80,0 th. UAH. |
I.Lahotskyy | May June |
35 | Production of construction documents and setting fire alarm | 100, 0 thousand. | A.Kudybin | 2-quarter |
36 | Installation of asphalt-concrete pavement in the parking lot | 85,0 thousand. | I.Lahotskyy | 2-quarter |
37 | Conclusion of the manufacture and installation of ramps | 25,0 thousand. | I.Lahotskyy | 2-quarter |
a house on the street. Січових Стрільців,25 у м.Івано-Франківську | ||||
38 | Repair of sewer Pidvalna | 10,5 thousand | A.Kudybin
N.Korolchuk |
2-quarter |
the houses on the street. Harkusha, 9 in Ivano-Frankivsk
and on the street. A.Krushelnytskoho, 3 the mind. Horodenka |
||||
39 | Work on strengthening the foundation, asfaltnogo cover adjacent to the foundation of the house
|
20,0 th. UAH. | N.Korolchuk
A.Kudybin |
3-quarter |
a house on the street. Shashkevych, 2 in Ivano-Frankivsk | ||||
40 | Estimating replacement mains, perform repair of the facade, purchase of materials | 10,0 th. UAH. | BUT. Kudybin,
V.Gava, N.Korolchuk
|
2-quarter |
41 | Carrying out partial replacement of the mains | 3-quarter | ||
42 | To conclude an agreement with the licensed organization for the repair of the facade – stucco restoration | estimate | A.Kudybin
N.Korolchuk |
2-3-quarter |
a house on the street. Shashkevych, 6 in Ivano-Frankivsk | ||||
43 | Preparation of design documentation and replacement of electrical equipment and wiring (if necessary) | 30,0 thousand. | V.Gava | 3-quarter |
44 | Installation of electric heating system (if necessary) | 80,0 thousand. | V.Gava, A.Kudybin | 4-quarter |
a house on the street. Independence, 5 in Ivano-Frankivsk | ||||
45 | To conclude an agreement with the organization licensed for the manufacture of project documentation for replacement of electrical equipment and wiring | 42,0 thousand. | V.Gava | 1-quarter |
46 | Examination of project documentation for replacement of electrical equipment and wiring | 2-quarter | ||
47 | To replace electrical equipment and wiring
|
3-quarter | ||
1 | 2 | 3 | 4 | 5 |
48 | Carry out a partial repair of the facade | 80,0 thousand. | N.Korolchuk, A.Kudybin | 3-quarter |
49 | To conclude an agreement to repair exterior balconies | estimate | A.Kudybin | 2-3-quarter |
50 | Carry out internal repairs staircase and corridors | 45,0 thousand. | N.Korolchuk | 1-2-quarter |
a house on the street. Galician, 45 the mind. Ivano-Frankivsk | ||||
51 | Укласти угоду з ліцензованою організацією на виготовлення проектної документації на проведення ремонту фасаду | estimate
|
A.Kudybin | 2-3-quarter |
52 | To conduct the examination of project documentation for the repair of the facade | |||
53 | Ensure repairing exterior balconies | estimate | A.Kudybin | 2-3-quarter |
in a building on Market Square, 8 the mind. Ivano-Frankivsk | ||||
54 | Ensure the repair of the facade 2 story | 5,0 th | N.Korolchuk | 3-quarter |
a house on the street. Vasyliianok, 62in m. Ivano-Frankivsk
|
||||
55 | Ensure the repair to bathroom 3 floor | 5,0 thousand. | Ya.Bugayçuk | 3-quarter |
56 | Провести встановлення системи пожежегасіння (включаючи засоби пожежегасіння) | 198,0 thousand. | Ya.Bugayçuk. A.Tymchiy | 2-quarter |
57 | Run Electrical repair floor, power systems, which are in disrepair | 9,0 thousand. | V.Gava | 3-quarter |
58 | Perform lifting equipment inspection
|
20,0 th. UAH. | Ya.Bugayçuk | 1-quarter |
To prepare the necessary documents to complete and periodic inspection | ||||
59 | Perform preventive roof and heating system boiler house. Ensure training system for the heating period | 5,0 th. pH.. | Ya.Bugayçuk | 3-quarter |
60 | Make an estimate on replacement windows | 250,0 th. UAH. | Ya.Bugayçuk
A.Kudybin |
2-quarter |
61 | To conduct the examination of project documentation for replacement windows | |||
62 | To replace windows | |||
63 | Perform maintenance in house, restore the inner face of the walls | 18,0 th. UAH. | Ya.Bugayçuk
N.Korolchuk |
August |
on the street. Maksimovic 10 and St.. Maksimovic, 10b |
||||
64 | Проведення робіт по визначенню об’єму та вартості ремонту дахового покриття ( перекрити 1200 м.кв.) | estimate | A.Kudybin
Ya.Bugayçuk |
June |
65 | Rebuild fences territory | 5,0 th. UAH. | Ya.Bugayçuk | May |
66 | Restore complex systems of fire | 8,0 th. UAH | Ya.Bugayçuk
A.Tymchiy
|
3-quarter |
1 | 2 | 3 | 4 | 5 |
67 | Resume electrical systems and outdoor lighting | 10,0 th. UAH. | V.Gava
Ya.Bugayçuk |
July |
68 | Production of documentation for permanent use land | 100.0 th. UAH. | S.Babelskyy | 1-4-quarter |
69 | Укласти угоди та забезпечити придбання: | |||
– миючого пилососа | 12,0 thousand. | S.Gayduk | 3-quarter | |
– спецодягу для працівників робітничих професій | 10,0 thousand. | S.Gayduk
A.Pidhirnyy |
2-quarter | |
– electrical | 50,0 th. UAH. | V.Gava | during the year | |
– Power | 10,0 th. UAH. | V.Gava | during the year | |
– aluminum battery and plumbing materials | 50,0 th. UAH. | A.Kudybin | during the year | |
– building materials | 150,0 th. UAH. | N.Korolchuk | during the year | |
– household chemicals | 60,0 th. UAH. | S.Gayduk | during the year | |
– washing machine | 10,0 th. UAH. | S.Gayduk | during the year | |
– 2 air power 3,5 кВт («12») для залу 7 floor | 24,0 th. UAH. | V.Gava | during the year | |
– 3 air power 2,5 кВт (9) (для кабінетів обласної ради) | 45,0 th. UAH. | V.Gava | during the year | |
– fire extinguishers, sleeves, fire barrels, Recharging of extinguishers | 198,0 th. UAH.
|
A.Tymchiy | 1-4- quarter | |
– office supplies | 20,0 th. UAH. | S.Gayduk | during the year | |
70. | Provision of health facilities, owned by the management and the operational manual operating assets | A.Pidhirnyy | during the year | |
71. | Ensuring celebrations, public meetings | I.Lahotskyy | during the year | |
72. | Accounting, financial reporting | V.Pasichnyk | during the year | |
73. | Maintenance personnel and administrative documents | N.Romaniv | during the year | |
74. | Zaprvadzhennya work site CE operating assets | V.Budzik | 1-quarter |
Babelskyy C.
A Kudybin. Тимчій А.
Гава В. Будзик В.
Korolchuk H. In Pasichnyk.
Лахоцький І. Гайдук С.
Бугайчук Я. Романів Н.